Crews were at El Rancho at sunrise on a cold October 28. They took down the 40-foot metal sign that had stood over the restaurant site for decades, then cut holes in the roof to lift out the brewery tanks. Canyon Courier reported that the sign came down in two pieces to make storage easier. "Each piece weighed about 750 pounds, or 1,500 pounds total," said Jarred Lilyhorn, parks operation manager at the Evergreen Park & Recreation District, who worked with the crane company on the job.
The park district is storing it for a building that does not exist yet: a green room beside the new performance pavilion at Buchanan Park, on Evergreen Parkway at Ellingwood Trail. For Hiwan and Bergen Park, Evergreen's best-known meeting place is being taken apart at the I-70 exit and put back together as a public room on the parkway they already use every day. The rebuild is happening in phases, and the El Rancho piece comes last.
Where the Pieces Went
El Rancho was built in 1948 as a mountain-themed automobile lodge and restaurant, and it became a major rest stop for travelers driving from the plains into the mountains. Today the building at 29260 U.S. Highway 40 is mostly empty, and parts of its roof are open to the weather. QuikTrip owns the land and plans a convenience store and gas station there.
The building's contents have already gone in several directions:
| Piece of El Rancho | Where it went |
|---|---|
| The 40-foot metal sign, about 1,500 pounds | Stored by EPRD for the future Buchanan Park green room |
| Brewery fermenters | Tommyknockers in Idaho Springs |
| Brewery silo | Cabin Creek Brewery in Georgetown |
| Chairs, dishware and other mementos | Sold to the public at EPRD's Oct. 10 sale |
| Chandeliers, bar, wood, foliage, benches, rockwork | Listed in February as items EPRD planned to save for the green room |
The two breweries took working equipment for their own use. The sign and the interior pieces stayed in Evergreen, and they stayed with a public agency rather than a private buyer. That choice matters more than anything else in the table.
A Restaurant's Job, Handed to a Park District
The plan was first announced on February 19 at a press conference on El Rancho's front steps, with county commissioners, the chamber president and EPRD board members present. District director Cory Vander Veen said engineers had found the structure too fragile to move, so the district would save as much of it as it could. "We're going to preserve everything we can — the sign, chandeliers, bar, wood, foliage, benches, rockwork," he said, according to Canyon Courier's account. "We will preserve the essence of El Rancho."
The salvaged pieces will go into a building designed to look like El Rancho, iconic sign included. It will be a green room for performers on the pavilion stage. When no show has it reserved, it will be open to the public and available to rent. "This will be open to the public and available to rent," Vander Veen said. "It'll serve as a green room, but will be available as a rental and accessible other times." QuikTrip did not charge EPRD for the items. The district said it would sell some of them and put the money into park funds.
At the same press conference, EPRD Board President Mary McGhee told Canyon Courier what the restaurant had meant: "It was always the place to meet people going between the airport and the mountains. We've lost that community hub." She also pointed out that El Rancho was "the only restaurant in America that has its own exit off a federal highway." The building once served as Evergreen's post office.
McGhee's description fits a building at an interchange, a place you stopped on the way between two other places. The green room will be in a neighborhood park. People will get to it from Evergreen Parkway, not from an interstate off-ramp. Nancy Judge, EPRD's director of community engagement, ran the October sale and was a regular at El Rancho herself. She described the change to Canyon Courier in terms of memories: "We know the residents of Evergreen have so many important memories from big-life events to Friday Night prime rib dinners. Evergreen Park and Rec plans to create a new space in Buchanan Park where many new memories will be created for generations to come."
Stage First, Room Later
The El Rancho room is the last piece of a much larger Buchanan Park project, and the first pieces are being finished this month. Here is how EPRD's own progress page lays out the order:
- Pavilion. An open-air, 2,250-square-foot stage for music and performing arts, with a house lighting package and electrical hookups for audio, video and lighting setups. EPRD expected it to be substantially complete in mid-November 2026.
- All-Wheels Skatepark. Substantial completion expected in late November or early December 2026.
- Playground, plaza, trails and swale improvements. Still in design and coordination, with work aimed at 2027. The adventure playground plans call for accessible surfacing, an embankment slide, a cairn rock climber and a splash pad next to it.
- Field house and gym. Permitting is underway, and construction is expected to start in early 2027.
- The El Rancho green room. A second phase with no set timeline.
Most of the money traces back to local voters. EPRD credits property tax revenue and ballot measure 6C, approved in 2023, for making the project possible. The district also lists outside grants, including $202,500 from the Jeffco Open Space Trails Partnership Program in January 2025. In August 2025, Friends of Buchanan Park raised more than $80,000, split among the inclusive playground, the performance pavilion and the skatepark. Jefferson County issued grading permits for the park and pool projects in September 2026.
In practice, the order means the stage is going up in a season when nobody will be performing outdoors. The sign that will someday hang beside it sits in storage until the second phase is funded and built. For now, the park section of Evergreen Parkway is a construction zone, and the El Rancho name is in a warehouse.
The Lake House Is the Template
The best preview of the future green room is a building Evergreen already uses. EPRD's renderings show a structure similar to the Evergreen Lake House in size, uses and availability. The Lake House is rented year-round for private and public events.
This December, much of Evergreen's holiday calendar takes place at the Lake House or on Bergen Parkway, where the green room is meant to fit in someday:
- Holiday Walk, Friday, Dec. 4, 5 to 9 p.m. Free. It starts with the tree lighting at Evergreen Lake House and continues downtown with performances, shopping, fire pits and seasonal food.
- Winterfest, Saturday, Dec. 5, 10 a.m. to 4 p.m. Center for the Arts Evergreen's free artisan market at 31880 Rocky Village Drive, with local vendors, Santa, crafts, food trucks, hot cocoa and live music.
- Santa Breakfast, Sunday, Dec. 6, at Hiwan Barn, 1552 Bergen Pkwy, with seatings from 8 to 9:30 a.m. and 10 to 11:30 a.m. A second date is Saturday, Dec. 19, at The Wild Game, 1204 Bergen Pkwy, with seatings from 8:30 to 10 a.m. and 10:30 a.m. to noon. Tickets are $28 per person for adults and children, the listing says children 1 and under are free, and tickets include breakfast, crafts, Santa and photos.
- Frostival, Saturday, Dec. 12, 11 a.m. to 3 p.m. At Evergreen Lake House, with crafts, live music, a holiday market and a bar serving festive drinks.
Skating on Evergreen Lake starts when the weather and ice allow. EPRD's 2026/27 rates are $15 for admission with no hourly limit, $20 with skate rental, $200 for a season pass that includes rentals, and $120 for a 10-punch pass. Children 4 and under skate free on individual admission. The district does not guarantee opening days or ice quality and does not refund passes, so the season pass only pays off if the lake freezes well.
The Lake House shows what a room run by the park district looks like in Evergreen: one building that hosts the Holiday Walk tree lighting on Dec. 4, Frostival's holiday market on Dec. 12, and private events the rest of the year. That is the role EPRD has described for the El Rancho room at Buchanan Park, with the sign as the main reminder of the restaurant it came from.
Projects like Buchanan Park slowly change how Evergreen gets used, and when your street sits close to them, they eventually show up in conversations about home values too. If you live near Bergen Park or Hiwan and want to know how changes along the parkway might affect your home, Perfect Denver Homes can walk you through it. Get your free home valuation, and we will put the numbers in neighborhood context.